The Trademark Build Process
BUILD FLOW CHART
Phase 1: Design
AVERAGE TIMELINE 2-4 MONTHS
Initial design meeting with Trademark Homes and designer
Preliminary layout design with designer
Complete 3D walkthrough
Adjustments from final design meeting
Draft review + budget check against Schedule B
Construction drawings + sign off
Interior material selections can be started
Phase 2: Pre-Construction
AVERAGE TIMELINE 4-6 WEEKS
The following are the steps our construction admin team works on to get your home ready to enter the construction phase. This pre-construction phase focuses on getting all the necessary paperwork submitted and administration completed. We also use this stage to start settling any allowances on your Schedule B and request quotes on customized features you have included in your plan.
Send final plans for window and door package and present to clients
Send final plan for engineering
Sign off on exterior selections
Send final plan for developer approval
Send final plans for plumbing and HVAC schematics
Documents collected and sent for energy modelling
Permit package submitted to municipality
Staking booked with surveyors
Phase 3: Construction
AVERAGE TIMELINE 7-9 MONTHS
The following construction stages are listed in the order they are typically completed in. The order can be changed due to material and trade schedules.
Excavation
Footing and piles installation
Foundation walls and concrete pour
Subfloor installation
Backfill
Garage grade beam
Framing walls, floors, roof trusses
Doors, windows, shingles installation
Rough-in mechanical: plumbing, HVAC, electrical
Basement slab pour
Framing checkout
Basement framing
Exterior finishes: soffit, fascia, siding, trim
Pre-drywall walkthrough
Insulation installation
Drywall hanging, mudding, taping
Paint prime
Trim and wall details
Kitchen installation
Paint finishing
Flooring and tiling
Final plumbing and electric install
Baseboard and touch-ups
Possession Day
Move-In Day
*Please note there may be some wait times between phases and during the construction stages. Timeline depends on the number of homes in the queue ahead of yours.*
Additional Acreage Stages
IF NECESSARY/REQUESTED
Dirt work
Services trenched and installed
Septic Installation
Well installation
Retaining walls
Road creation
The following are items that could be completed during or after the building depending on the time of the year:
Seasonal Items
Garage slab
Driveway and flatwork
Stucco and parging
Stone work
Completed decks, stairs, railing
Final Grade
Glossary
DEVELOPER APPROVAL
All homes in a new development area are required to be approved by the developer to ensure they meet neighborhood architectural guidelines. In the case of Infill homes the City will approve the design of the home in the permit application and verify it meets the new bylaw guidelines.
ENERGY MODEL
According to the National Building Code 9.36 all new homes and additions are required to have an energy model completed to ensure the home meets the national standard of energy efficiency.
EXCAVATION
AKA “The Big Dig”
FOOTING AND PILES (according to engineer specs)
The foundation walls sit on the footing (and piles if required). This is designed and spec’d by the structural engineer.
FOUNDATION WALLS AND CONCRETE POUR
The basement walls are constructed using concrete forms. The forms are placed directly on the footing and filled with concrete and rebar. In the winter months this stage will also include hoarding (covering) the basement with insulated tarps and heating the concrete as requited. Once complete the forms are removed.
FOUNDATION SUBFLOOR
The framers will come and install the main floor trusses and subfloor material.
BACKFILL
Material being placed against the foundation.
GARAGE GRADE BEAM
This stage could also be completed at the time of the foundation pour. A grade beam is the lower concrete portion of the garage walls that the wood walls sit on.
FRAMING
Constructing the walls, floors, roof trusses, etc. Making it look like a home!
DOOR AND WINDOW INSTALL
Framing crew will install doors and windows in their openings. Another crew will come and do blue-goo installation and ensure doors and basement windows are set properly.
ROUGH-IN MECHANICAL
Plumbing + HVAC
Many different plumbing crews will be in the home at this time. This includes waterlines + ABS crews, HVAC crews, fireplaces and tubs being installed, gas lines, waterline and water testing, etc.
Electrical
Electricians will run wiring according to the construction plans for lights, switches, cat5, etc.
BASEMENT SLAB POUR
Once plumbing rough-ins are completed in the basement the basement concrete slab will be poured.
FRAMING CHECKOUT
A framing checkout crew takes care of all the small framing details like niches, fireplace framing, bulkheads, checks doors + window opening sizes, adds backing for hanging areas (closets, railings, TV, etc). Another term this stage could be called is “Back Framing”.
EXTERIOR FINISHES
Soffit, Fascia, paper/wire/stucco, paper/siding, trim, wood details.
PRE-DRYWALL WALKTHROUGH
This is our official meeting on site with James + Melissa and the clients. At this walk through we will go over the home in great detail looking at all the electrical, door swings, closet layouts, wall details, etc. We make sure the house is ready to be finished exactly how you envision it. This walkthrough typically takes about 2-4 hours depending on the house size. It also needs to be scheduled during daytime business hours so be prepared to book some time off work if needed.
INSULATION
Insulation (batt/poly or spray foam) is installed in the home.
DRYWALL
This stage typically takes about 2 weeks to complete. This includes hanging the drywall, mudding and taping.
(Possession date will be given at the end of this stage)
TRIM AND WALL DETAILS
Our trim carpenter will spend time in the house installing all doors, casing, shelving, and completing any wall details like wainscoting, shiplap and board and batten. Some areas could get baseboard depending on the flooring product being installed.
KITCHEN
This stage could fit in a few different places. The Kitchen will be installed and inspected for defects. Before possession they will also come back and make any final adjustments needed on site.
PAINT
Pretty self explanatory but all the walls will be rolled, the casings, baseboards and wall details will be sprayed.
TILING/FLOORING
This stage could also be completed in a few different steps. This stage also includes areas like custom tile showers and backsplashes.
FINAL PLUMBING INSTALL
All the taps, toilets, sinks, etc. installed.
FINAL ELECTRICAL INSTALL
All the lighting fixtures and potlights installed.
BASEBOARD AND TOUCH UPS
Our Finaling Team will spend the weeks before possession in your home doing all the last minute details such as caulking, silicone, paint touch-ups, and going through our turn over check sheet to make sure the home is ready for occupancy.
POSSESSION DAY
Meet the Trademark Team at the end of the day (typically 4:00 pm) and get the keys to your house. We will walk through the home and show you all the details you need to know. Most importantly we will celebrate this moment together!
MOVE IN DAY
The day after possession it’s safe to schedule the movers and let the fun begin!